MAHARASHTRA KRISHNA VALLEY DEVELOPMENT CORPORATION, PUNE.
Sangli
Irrigation Circle, Sangli.
Tembhu
Lift Irrigation Project, Tal.
Karad, Dist. Satara.
|
Introduction:
Tembhu Lift irrigation Scheme has been proposed to irrigate the drought
prone area from RL 650 m to 855 m i.e. above the command area of
Takari Lift Irrigation Scheme. The project is administratively approved
in 1996 for Rs. 1416.59
Crores. The scheme envisages lifting of 22
TMC water from Krishna river to Irrigate 80472
Ha.
of lands from, Karad,
Kadegaon, Tasgaon,
Khanapur, Atpadi,
Kavathe Mahankal,
Sangola Talukas of
Satara, Sangli &
Solapur Districts. The water requirement is met with
from Koyna, Wang and Tarali
storage dams. The revised administrative approved cost is Rs. 2106.09 cores
which includes Rs. 1750 crores for work portion. The
upto date expenditure on the project is about
Rs.1413.31 crores (work portion.)
The scheme
consists of constructing Barrage across Krishna
river at village Tembhu,
Tal. Karad, Dist. Satara
& Pump House sat various stages Rising main, Tunnels
& canal, distributory network and the water is
lifted in five stages at different location.
Salient Features:
-
Total Command Area
: 80472 Ha.
-
Discharge
: 57.3
Cumecs
-
Total No. of Pumps
: 111 Nos.
-
Power required
: 154 MW
-
Total Length of canal
: 409 Km.
Position
of works:
The Project
work were started in 1996. The head work & canal of all five stages were
started simultaneously so as to complete the work before May 2000 in order to
utilize water as per Krishna Water Dispute Tribunal Award. The present status of
the project is given below.
|
STAGE WISE TECHNICAL DETAILS
|
Sr. No. |
Details |
Stage I |
Stage II |
Stage III |
Stage IV |
Stage V |
Total |
|
1 (A) |
1 (B) |
3 (A) |
3 (B) |
|
1 |
Storage
Details |
Through
Tembhu Barrage |
Through
Sump Well |
Through
Link – I Canal |
Through
Link – II Canal |
Through
Link- III Canal |
Through
feeder Canal |
Through
Feeder Canal |
|
|
2 |
Pump House |
|
|
|
|
|
|
|
|
|
|
a) No. of
pumps (Regular+ Stand by)
b) H.P.
c) Total
H.P.
d)
Electricity required (MV) |
30
+
3 |
39
+
3 |
2
+
1 |
20
+
3 |
4
+
1 |
3
+
1 |
4
+
1 |
99
+ 1 |
|
33 |
39 |
3 |
22 |
5 |
4 |
5 |
100 |
|
1950 |
2200 |
1400 |
1940 |
1990 |
1075 |
1235 |
|
|
18500 |
79200 |
2800 |
38800 |
7960 |
3225 |
4940 |
195425 |
|
45.82 |
62.04 |
2.19 |
36.62 |
- |
2.53 |
3.87 |
153.07 |
|
3 |
Rising
Main |
|
|
|
|
|
|
|
|
|
|
Length M. |
2050 |
230 |
1700 |
3740 |
1540 |
1290 |
2300 |
37010 |
|
Dia. M |
2.5 |
2.5 |
1.5 |
2.5 |
2.2 |
1.8 |
1.8 |
|
|
Lines |
6 |
6 |
1 |
4 |
2 |
1 |
1 |
|
|
4 |
Designed
Static Head |
60.83 |
86.61 |
57.98 |
63.67 |
30.67 |
37.47 |
68.33 |
|
|
5 |
Discharge |
57.37 |
57.37 |
2.88 |
35.22 |
14.91 |
5 |
4.32 |
|
|
6 |
Length of |
-- |
Link Canal
I 15 Km Link cancl II 30 Km |
Surli
23 Kamathi 16 Km |
Stage 3 A
to Ghanad 18 Atpadi
Left 15 Ghanad Hivtad
32 Sangola 45 K.Mahan
kal 40 |
Khanapur
Tasgaon 106 Km. |
Stage 4 to
5 Feeder canal 7 Kachare
wadi 35 Km. |
Gorewadi
25 Km. |
Total 409
Km. |
|
7 |
Command
Area |
|
|
Taluka |
|
|
Karad |
- |
- |
600 |
- |
- |
- |
- |
600 |
|
|
Khanapur |
- |
- |
- |
- |
12975 |
4000 |
2000 |
18375 |
|
|
Kadegaon |
- |
5925 |
3400 |
- |
- |
- |
- |
9325 |
|
|
Tasgaon |
- |
- |
- |
- |
7700 |
- |
- |
7700 |
|
|
Atpadi |
- |
- |
- |
3652 |
- |
- |
- |
16000 |
|
|
|
- |
- |
- |
12348 |
- |
- |
- |
- |
|
|
K.Mahankal |
- |
- |
- |
7872 |
- |
- |
- |
7872 |
|
|
Sangola |
- |
- |
- |
20000 |
- |
- |
- |
20000 |
|
|
Total |
- |
5925 |
4000 |
43872 |
20675 |
4000 |
2000 |
80472 |
Present
Position of Stage I & II of Tembhu Project,
Karad
|
Sr. No. |
Name of
Work |
Present
position of work |
|
1 |
Tembhu
Barrage |
Work is
completed |
|
2 |
Approch
channel 1 (A) |
Work is
completed |
|
3 |
Pump House
1 (A) |
PH (I) is
partially commissioned |
|
4 |
Control
room 1 (A) |
Civil work
completed 17 panels are installed, Other work in progress. |
|
5 |
Pressure
filter 1 (A) |
50% work
completed. |
|
6 |
Anti surge
1 (A) |
IRM is tested. |
|
7 |
Switch
yard 1 (A) |
Work is
completed.
The switch
yard is changed. |
|
8 |
Manifold 1
(A) |
Civil work
100% completed. Mechanical work in progress. Work for 1 row is completed
100%. |
|
9 |
Rising
Main 1 (A) |
Civil work completed. |
|
10 |
Railway
crossing 1 (A) |
Civil work
is completed. |
|
11 |
Pump House
Stage 1 (B) |
Civil work
completed. All pumps are installed. 6 pumps are commissioned. |
|
12 |
Control
room 1 (B) |
Civil work
is completed & all panels are fixed - 5 panels tested. |
|
13 |
Switch
yard 1 (B) |
Work is
completed.
The switch
yard is changed. |
|
14 |
Pressure
filter 1 (B) |
Work is
completed. |
|
15 |
Anti surge
1 (B) |
Work is
completed and IRM is tested. |
|
16 |
Manifold 1
(B) |
Work for 1
line is completed and other is in progress. |
|
17 |
Rising
Main 1 (B) |
Work
completed. |
|
18 |
Delevery
Chamber 1 (B) |
Work
completed. |
|
19 |
Kambale
Tunnel |
Work
completed 100% |
|
20 |
Link
canal-I Km. No. 1 to 15 |
98% work
is completed. |
|
21 |
Link
canal-II Km. 1 to 23 |
95% work
is completed. |
|
22 |
Pump House
Stage – II |
Work
is completed. |
|
23 |
Control
Room II |
Work
is completed. |
|
24 |
Swich
Yard – II |
Work
is completed. |
|
25 |
Manifold –
II |
Work
completed. |
|
26 |
Rising
Main – II |
Work is
completed |
|
27 |
Anti Surge
– II |
Zero velocity
valve is fixed. |
|
28 |
Delivery
Chamber – II |
Civil work
is completed |
|
29 |
Surali
canal – II K.M. 1 to 23 |
Work is
completed |
|
30 |
Kamathi
canal–II K.M. 1 to 15 |
Work is
completed |
|
31 |
State
Highway Road crossings |
Work
completed |
|
32 |
M.D.R./O.D.R.
Road crossings |
Completed |
|
33 |
Khanapur
– Tasgaon K.M. 11 to 42 |
K.M. 11 to
20 Earth work completed 21 to 42 work
are in
progress. |
|
34 |
Khodashi
Gated weir |
Work is in
progress |
|
35 |
Flood
protection wall for Karad Town |
Tender
process is completed 50%. Work is Completed. |
|
Sr.
No. |
Name
of Work |
Present position of work |
|
1 |
Pump
House Stage – III |
90%
work completed. |
|
2 |
Rising
Main Stage – III |
Work
completed. |
|
3 |
Devekhindi
Tunnel |
Excavation completed & lining is in
progress. |
|
4 |
Stage III
A to Ghanand Tank 19 K.M. canal |
80% work
completed. |
|
5 |
Ghanad-Hivthad
canal – 32 K.M. |
77% work
completed. |
|
6 |
Kavthe-mahanakal
canal 40 K.M. |
KM No. 5
to 19 are in
progress. |
|
7 |
Atpadi
canal 15 K.M. |
KM 3 to
10 are completed. |
|
8 |
Pump
House Stage – IV |
55% work
completed. |
|
9 |
Rising
Main – V |
Work
completed. |
|
10 |
Feder
canal stage – IV to V-7 K.M. |
68% work
completed. |
|
11 |
Kacharewadi
canal – 35 K.M. |
--- |
|
12 |
Pump
House Stage – V |
45% work
completed. |
|
13 |
Rising
Main – V |
Work
completed. |
|
14 |
Gorewadi
canal 25 K.M. |
--- |
|
Sr.
No. |
Distribution
Work |
Present position of work |
|
1 |
Surali Canal |
80% |
|
2 |
Kamathi Canal |
1% |
|
3 |
LK - I |
1% |
|
4 |
LK - II |
1% |
|
5 |
Khanapur Tasgaon Canal |
0%
|
|
6 |
Ghanand Hivathad Canal |
|
7 |
Atpadi Canal |
|
8 |
Sangola Canal |
|
9 |
Kavathemahankal Canal |
|
10 |
Visapur Punandi LIS |
|
11 |
Kacharewadi Canal |
|
12 |
Korewadi Canal |
Year wise Expenditure of the Tembhu
Project
Tembhu Lift Irrigation Project
Expenditure Statement
Rs. in Crore
|
Year |
Year wise
Expenditure |
Total
Expenditure |
|
Work Portion |
With ETP |
Work Portion |
With ETP |
|
1996-97 |
10.86 |
13.40 |
10.89 |
13.40 |
|
1997-98 |
104.09 |
128.45 |
114.95 |
141.85 |
|
1998-99 |
65.51 |
80.84 |
180.46 |
222.69 |
|
1999-00 |
145.80 |
179.92 |
326.26 |
402.60 |
|
2000-01 |
146.10 |
180.29 |
472.36 |
582.89 |
|
2001-02 |
72.59 |
89.58 |
544.95 |
672.47 |
|
2002-03 |
43.20 |
53.31 |
588.15 |
725.78 |
|
2003-04 |
56.92 |
70.24 |
645.07 |
796.02 |
|
2004-05 |
10.75 |
13.27 |
655.82 |
809.28 |
|
2005-06 |
117.07 |
144.46 |
772.89 |
953.75 |
|
2006-07 |
117.86 |
140.50 |
886.75 |
1094.25 |
|
2007-08 |
21.35 |
26.35 |
908.10 |
1120.60 |
|
2008-09 |
46.80 |
57.75 |
954.90 |
1178.35 |
|
2009-10 |
91.00 |
112.29 |
1045.90 |
1290.64 |
|
2010-11 |
99.41 |
122.67 |
1145.31 |
1413.31 |
|
AIBP - (Accelerated Irrigation
Benefit Program)
The scheme is partially commissioned and 1020Ha area is irrigated. Now
planning commission of Central Govt. is cleared the project for AIBP
Assistant of amounting Rs.1972.60Crs. As per this planning the project
will be completed upto March 2016. The AIBP programme of the project is as
below. |
|
Year |
Central
Govt. Assistant |
State Govt.
Assistant |
Total |
Irrigation
potential to be created |
|
2011-12 |
112.5 |
12.5 |
125 |
1250 |
|
2012-13 |
309.01 |
34.34 |
343.25 |
7655 |
|
2013-14 |
433.02 |
48.11 |
481.13 |
21000 |
|
2014-15 |
447.28 |
49.7 |
493.98 |
23095 |
|
2015-16 |
473.53 |
52.61 |
526.14 |
26452 |
|
Total |
1775.34 |
197.26 |
1972.6 |
79452 |
|